Ahmedabad, Nov 16 (SocialNews.XYZ) Adani Green Energy Limited (AGEL) said on Monday that no component of the Tarali pumped storage project (PSP) in Maharashtra falls within any notified Protected Area, and no forest land is involved in the project.
In a fresh statement, an AGEL spokesperson said that necessary permissions/NOCs relating to land use and statutory requirements have already been obtained from the competent authorities.
"The project has also obtained Environmental Clearance (EC) on 11.02.2025. Based on this, the Consent to Establish (CTE) from Maharashtra Pollution Control Board (MPCB) to start the project work was issued on 07.04.2025. The construction activities have commenced only after obtaining all the requisite approvals from concerned authorities,” the company spokesperson said.
In parallel, the wildlife clearance process has also been duly initiated and pursued as part of the Environmental Clearance (EC) compliance process, according to AGEL.
“The proposal for Survey and Investigation activities was submitted in January 2025 and subsequently recommended by the State Board for Wildlife. The proposal for the project has since been submitted to the National Board for Wildlife (NBWL) and is currently under consideration,” the spokesperson further added.
According to the Adani Group company, the project is being developed in full compliance with applicable statutory requirements and the directions of the competent authorities.
Last week, AGEL vehemently denied allegations that it lowered the cost of the Tarali PSP in Maharashtra in order to diminish statutory obligations.
A company spokesperson said that the allegation that the company sought to revise project costs downwards to diminish statutory obligations is “completely misleading”.
The spokesperson said that the online proposal in the forest/wildlife portal was solely for site investigation purposes, while the State Board for Wildlife (SBWL) considered total project costs of Rs 5,675 crore.
“Since site investigation costs are around 1 per cent of project costs, therefore clarification of the project Rs 56.75 crore representing solely the site investigations and survey costs, for the online proposal was provided,” the Adani Group company spokesperson said.
Source: IANS
About Gopi
Gopi Adusumilli is a Programmer. He is the editor of SocialNews.XYZ and President of AGK Fire Inc.
He enjoys designing websites, developing mobile applications and publishing news articles on current events from various authenticated news sources.
When it comes to writing he likes to write about current world politics and Indian Movies. His future plans include developing SocialNews.XYZ into a News website that has no bias or judgment towards any.
He can be reached at gopi@socialnews.xyz