Cabinet nod for revised cost estimate of Uttarakhand hydel plant

Cabinet nod for revised cost estimate of Uttarakhand hydel plant
New Delhi, March 6 (IANS) A Union Cabinet panel on Monday approved the first revised cost estimate of Rs 2,717.35 crore for the 400 MW Koteshwar hydro-electric power project in Uttarakhand, an official statement said.

"The Cabinet Committee on Economic Affairs has approved the Revised Cost Estimate-I of 400 MW Koteshwar Hydro Electric Project (HEP) in Uttarakhand at an estimated completion cost of Rs.2,717.35 crore," a Coal Ministry statement here said.

The project is being implemented by state-run Tehri Hydro Development Corporation.

 

"In addition to additional generating capacity of 400 MW of peaking power Koteshwar HEP will regulate releases from Tehri reservoir for irrigation and drinking water supply," the statement said.

"The project has already been commissioned fully in March, 2012. Only balance works are to be done which are not linked with operation of the plant but essential for safety and completion of the project," it added.

(This story has not been edited by Social News XYZ staff and is auto-generated from a syndicated feed.)

Facebook Comments
Cabinet nod for revised cost estimate of Uttarakhand hydel plant

About VDC

Doraiah Chowdary Vundavally is a Software engineer at VTech . He is the news editor of SocialNews.XYZ and Freelance writer-contributes Telugu and English Columns on Films, Politics, and Gossips. He is the primary contributor for South Cinema Section of SocialNews.XYZ. His mission is to help to develop SocialNews.XYZ into a News website that has no bias or judgement towards any.